Construction Updates on Our Lima Branch

 

 Expansion Lima West with Stone

First National Bank Plans Expansion to Lima

March 29, 2022 - First National Bank is pleased to announce the future site of its newest full-service community bank at 2580 Eastown Road, Lima. Construction is expected to start in June 2022 and the branch is slated to open in December 2022. Click here for more details.

 

 Expansion Lima West Board of Directors Groundbreaking

First National Bank Holds Groundbreaking Ceremony

June 13, 2022 - First National Bank held their groundbreaking ceremony. Pictured are (left to right) Jared Lehman (FNB Board of Directors), John Arnold (Chairman of FNB Board of Directors), Pete Suter (Chairman of Pandora Bancshares, Inc.), Randal Verhoff (FNB Board of Directors), Brendon Matthews (EVP, Senior Lender at FNB) and Todd Mason (President & CEO at FNB).

 

 Expansion Lima West 06.15.22

First National Bank Begins Construction

June 15, 2022 - Construction has begun!  Equipment arrived at the site and ground is being leveled.

 

 Expansion Lima 06.30.22

Early Site Work in Process at First National Bank

June 30, 2022 - The construction crew has been busy staking the building pad, getting the utilities ready and digging the footers to get ready for concrete.

 

 Expansion Lima West 07.12.22

Concrete Footers and Walls

July 12, 2022 - The building footprint is really taking shape. Concrete walls and footers have been poured.

 

 Expansion Lima West 8.1.22

Prepping the Building Pad

August 1, 2022 - Last week, the building pad under-slab rough-ins for plumbing and electrical were completed. This week the building slab will be prepped and poured and the anchor bolts will be set for the structural steel installation, which should begin next week.

 

 Expansion Lima West 08042022

Building Slab was Poured

August 4, 2022 - The building slab was poured last week and the structural steel for the building will be placed this week.

 

 Expansion August 18 2022

Structural Steel and Columns Placed

August 18, 2022 - The structural steel and columns were placed. They are working on the rest of the steel framing.

 

 Expansion 08.31.22

Framing

August 31, 2022 - We have walls! The construction crews are framing now and it's starting to look like a building.

 

 Expansion 09.02.2022

Walls and Roof Framed

September 2, 2022 - Rough carpentry is close to being finished with all exterior walls framed and the roof framing up. With that work finishing up, they will be roughing in electrical and plumbing in the coming weeks.

 

 Expansion 09.14.2022

Building is Wrapped

September 14, 2022 - The building wrap was completed on the exterior. They will be starting on the metal roof soon.

 

 Expansion 09272022

Metal Roof Installed 

September 27, 2022 - The blue metal roof panels were installed. The interior electrical rough-ins were completed, along with some interior drywall and insulation.  Next, they will be installing the fascia and gutters for the roof while continuing the interior drywall and soffits. Then they will be doing some sitework, as well as some electrical rough-ins for site lighting.

 

 Expansion 10.03.22

Interior Rough-Ins

October 3, 2022 - Above you can see the inside of the branch, where HVAC rough-ins and the electrical rough-ins for interior walls are being completed. Drywall will be hung next.

 

 Expansion 10.21.22

Concrete Work 

October 21, 2022 - Concrete curbs, sidewalks, and drive-thru areas are in the process of being poured and finished. The stonework on the outside on the branch is in process.

 

 Expansion 10.26.2022

Inside Drywall Progress

October 26, 2022 - Drywall is almost complete. The team was able to do a walk-thru and visualize the interior space.

 

 Expansion 10.27.2022

Bricklaying Work Has Begun

October 27, 2022 - The brick on the outside on the branch is being laid.

 

 Lima West Expansion 11.02.2022

Blacktop Complete

November 2, 2022 - The blacktop around the new building was completed.

 

 Lima West Expansion 11.15.22

Windows and Stonework

November 15, 2022 - The stonework around the building is being laid. The aluminum storefront and windows are being installed. Inside the bank, they are installing ceiling grid and interior doors and frames. The walls will be primed to be ready for paint. Mechanical, electrical, and plumbing work will also continue. 